PROJECT ID | PROJECT | ADDRESS | GRANT | AMOUNT | RELEASE DATE | SUBMITTAL DUE DATE | SELECTION DATE | SELECTED | STATUS |
ISL-02 | RFP_ Sustainability and Recovery Coordinator Support Services Contractor | N/A | CALOES JUMPSTART PREPARECA | TBA | 09/19/24 | 10/25/24 | 11/19/24 | ||
ISL-01 | RFP for City Website | City Hall | CETF | TBD | 09/12/24 | 10/15/24 | 10/22/24 | ||
RFP for Engineering Main St Lighting Planters and Seating Project – Isleton | Main St | Sacramento Housing & Redevelopment Agency | 30,000 | 08/30/24 | 10/04/24 | 11/12/24 | |||
RFP Main Street Rehab & Streetscape Design & Engineering | Main St | SACOG | 30,000 | 05/29/24 | 06/28/24 | 07/09/24 | Vertical Pacific | Waiting for Draft Contract for CC approval | |
RFP_Isleton-2024-05-29-19-15-03_final | Main St. | SACOG Managed Funds | 100,000 | 05/29/24 | 06/07/24 | 07/03/24 | Green Dot | Contract Signed | |
Sewer Rate Study RFQ | City | TBD | TBD | 02/05/24 | 03/01/24 | 03/26/24 | CANCELED | City Approved Grant from RCAC | |
Residential Infill Development Facilitation Program for the City of Isleton | Main St | SACOG Green Means Go | 100,000 | 11/30/23 | 01/19/24 | 02/13/24 | None Selected | ||
Father’s Day Event RFP | City | N/A | TBD | 11/16/23 | 12/07/we | 12/12/23 | Isleton Foundation LLC | ||
CIP-23-11 | Gen Plan – Draft Zoning Code Update | Citywide | HCD SB2 | 65,000 | 03/24/23 | 04/21/23 | 06/13/23 | Interwest | Contract Signed |
CIP-23-08 | Gen Plan – Wastewater Master Plan | Citywide | HCD SB2 | 35,000 | 03/24/23 | 04/21/23 | 06/13/23 | Bennett Engineering | Contract Signed |
CIP-23-10 | Gen Plan – Storm Drain Master Plan | Citywide | HCD SB2 | 50,000 | 03/24/23 | 04/21/23 | 06/13/23 | Bennett Engineering | Contract Signed |
CIP-24-02 | Wilson Park Rehabilitation Project | 1 Andrus Cir | OGALS Prop 68 | 178443.39 | 02/07/23 | 03/31/23 | 04/11/23 | Consolidated Engineering | CC Bid Awarded 07/11/23 Project Start 10/01/23 |
Main St Redesign & Rehab | Main Street | Caltrans Sustainable Communities Grant | 240,000 | Street Plans | |||||
CIP-23-04 | Boat Launch Feasibility Study | 1st Street | DWR | 200,000 | 11/23/22 | 12/20/22 | 04/11/23 | Moffatt & Nichol | Contract Pending Signatures |
N/A | Cannabis Social Equity Assessment Study | Citywide | GOBIZ | 22,000 | 03/14/2022 | 04/22/22 | 05/10/22 | CA Humboldt Center for Rural Policy | Completed |
CIP-21-01 | Isleton Local Roads Safety Plan | Citywide | CALTRANS LRSP | 80,000 | 04/23/21 | 05/17/21 | 06/08/21 | TJKM | Completed |
CIP-24-01 | Delta West Road Rehabilitation | West of Delta | None | 756,000 | 01/15/21 | 02/12/21 | 02/23/21 | Big Valley Electric | Completed |